Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

List of activity for sub structure work

No replies
Milind Pandhare
User offline. Last seen 8 years 38 weeks ago. Offline
Joined: 29 Aug 2005
Posts: 54
Groups: None
Activity ID Activity description

*mobilisation work*
MOBI-01 Site Mobilisation
MOBI-03 Fencing work
MOBI-02 Establish Temporary Servicies

*Earth work*

EARTH-03 Shoring ( I- Section Concrete pannel )
EARTH-02 Priliminary Earth Work
EARTH-04 1st Phase Excavation
EARTH-05 2nd stage Excavation & concrete panel instlation
EARTH-07 Carting Excess Excavated material
EARTH-06 Dewaterring
EARTH-08 Formation of Deep Area
EARTH-09 Compaction & Formation for Raft bed
*Foundation work*
FOUND-02 Guniting
FOUND-01 PCC Deep Area
FOUND-03 PCC below RAFT
FOUND-05 Rubberised Bitumen Coating
FOUND-06 Waterproofing & Screed Protection
FOUND-04 Vertical area water proffing
FOUND-07 Steel work for RAFT
MEP-01 Drainage pipe laying and testing (UG Drainage)
FOUND-08 Raft Slab Casting (Part A&B)

*Basement work*

SUB-01 Retaining Wall
SUB-06 Ramp Work
SUB-02 Shear Wall & Lift Core Wall
SUB-03 steel work for column
SUB-04 Form work for column
SUB-05 Column casting For GF Slab
SUB-07 Decking Work for G.F Slab
SUB-08 Steel Work for G.F Slab
SUB-09 MEP sleves & conduits for G.F Slab
SUB-10 Ground Floor Slab Casting
SUB-11 Deshuttering
SUB-12 Ramp Side RCC wall
SUB-13 Rcc planters & side wall / upstaand