Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Actual costs after activity has finished (lumped on Data Date)

No replies
Neil Hendry
User offline. Last seen 4 years 50 weeks ago. Offline
Joined: 9 May 2012
Posts: 12

Hi

I would appreciate some help from any of you guys regarding a issue I am having with spreading actual costs (version 6.2.1)

 

I have spread a resource (material @ £1/ea) on a WBS Summary Bar that encompasses the activity bars in question however when I look at the actual cost distribution in resource assignment view some of the actual cost has been lumped on the data date (which is roughly a year after the activities had finished)

There are £0 remaining costs (as the scheme has finished)  - I have made sure that planned finish = actual finish and have checked that I haven't stored period actuals in the future by mistake.

How can I get rid of this "future actual" and ensure the entire actual sum is spread over the Actual dates?

I am unable to edit the spread manually as the values are greyed out.

Any help or pointing in the right direction would be much appreciated.

Thanks

Neil