how does p6 define which is the driving predecessor?

M
Mateo Sanin 👤 Member for 15 years 6 months

Hi all,

 

I'm kind of new to P6 and I came across this slight problem:

I have an activity with two predecessors both of which I am unsure when the ultimate start date will be (it will be defined at a later stage), this activity should begin start to start with whichever of the two predecessors starts first.

When I add both predecessors and set them start to start the activity always lines up start to start with the predecessor which starts the LATEST. Is there any way to change this?

I've looked around quite a bit and haven't been able to find anything.

 

Thanks for your helo