Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Creating deliverable milestones within a work activity....explained below.

No replies
Brian Walkin
User offline. Last seen 8 weeks 3 days ago. Offline
Joined: 27 Dec 2017
Posts: 33
Groups: None

I have an activity of work which has a defined begining date and duration. For this work there are several deliverable document items. I have set these as start miletones and related to the work activity with a start to start relationshbip.  The documents themselves don't alweays have successors but I don't want to leave an open end and thought i would coule make a Finish to Finish activity with the work activity. However P6 not letting me do that. I have never come accross this and not sure how to deal with it. i do need to show the deliverables as activities with milestone dates to track progress and of course some do have significant successor ties but not all.   

 

any guidance / suggestions appreciated.

 

work activity (5 weeks) 

SS deliverable milestone A

SS deliverable milestone B

SS Deliverable milestone C

 

a,b, and c need to be completed before the work activity can end.