Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

EVM Work To Go formula

No replies
sam dsoza
User offline. Last seen 6 years 4 weeks ago. Offline
Joined: 20 Jun 2006
Posts: 55
Groups: None

My client would like me to provide % contingency left on the project with respect to BAC and EAC.

The formula would then be (contingency remaining) / (work left to go)

Now

For BAC, fomula would be (BAC - EV) for remaining work to go.

For EAC, would the formula be (EAC - EV) or (eac - actual costs) for work left to go?

Please note that EAC calulation is manual which is a sum total of (actual cost to date) + (estimate of work left to go) + (estimate of future known baseline change)

Thanks to the EVMS experts in advance.