Project tracking - Updating in MPP 2003

Hi,

I need help for project update,

I have a master schedule of 1350 activities with only task's (no resources and cost) I have saved baseline and inserted column

of Baseline duration and baseline start and finish, and also inserted actual duration and actual start and finish columns and

%age complete for tracking, I m updating actual data like %age complete inserting in activities and start date and finish date as per actual progress. I have also inserted column of start and finish for future progress (to see as planned start and finish) also overall project.

My question is that I have inserted progress in actuals column but in start and finish column (for Future start and finish according ot actual) is same also those activities which dates have been passed and start and finish columns like freezed.

 

thanks and regards,

Mkumar Khatri

Featured Partner

Top Posters

Tijo Kurian
11 posts
Zainab El-Beialy
3 posts
Kamlesh Parmessur
4 posts
MR JUDE C ANYAEGBU
0 posts
GeoVe
0 posts
Ashkan Mohammadi
0 posts
Jeroen De Bauw
0 posts
Senior Planning Engineer
0 posts
Kristian Mcwilliams
1 posts
dagogo dan - jumbo
2 posts