Splitting activities in P6

No replies
Uduma Shariff
User offline. Last seen 12 years 17 weeks ago. Offline
Joined: 31 May 2012
Posts: 2
Groups: None

Hi

The normal form of splitting activities is to use the 'Suspend' and 'Resume' functions in P6. However I find that this does not work in my P6 system.

The activity does not indicate a stop and restart date in my Gantt chart.

Is there something I am doing wrong.

Any help will be greatly appreciated

Thanks

 

Uduma