Dear All,
I will like to some information on the following situation:
I have a project that involves fabrication at workshop than this material has to get assembled at site, before the asseblying the civil works should be completed.
I have linked assebblying to civil works : Civl works--> F.S-->Assemblying at site
fabrication is linked to assemblying: Fabrication---F.S-->Assemblying
Fabrication is starting with a constrain (start no earlier than a date) , that i fixed at the time of basline adjsting that fabrication was starting with finsih of civil works at site and the material was coming and getting assembled at site without having need to stock it.
Now in actual my civil works got delayed, which means assmbleying cant start, but fabrication process is at same satrting date and if this continues i will have stocks at site. i wnat to see a situtaion that fabrication also gets started late equal to delay of site avaialbilty to start the assemblying:
what would be best practice in your views
Regards