Team Usage - EPPM

No replies
Michael Petzer
User offline. Last seen 3 years 33 weeks ago. Offline
Joined: 29 Apr 2021
Posts: 5
Groups: None

Hi There,

Currently using EPPM vs19

When viewing the resources at  'Team Usuage' the chart defaults to Two years (Q3 2021 to Q2 2023)?

Current project im working on has duration of 5years, looking to download team usage for this time.

When viewing the same data under the assignments tab, no issues.

Is there any settings I have missed to allow me to view the reources total allocated units/quarter over the five years.

Appreciate any assistance.....