Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Baseline Types

No replies
Tanveer Ahmad Niazi
User offline. Last seen 7 years 16 weeks ago. Offline
Joined: 15 Dec 2005
Posts: 151
Groups: GPC Qatar

Hi Planners

Would anyone please tell me what are different baseline types (Customer Sign-Off, Management Sign-off, Prior Month Update, Initial Plan etc.) for.

Cheers - Tanveer