Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Cost Control MS Project 2007

No replies
Maarten van Wyk
User offline. Last seen 13 years 6 weeks ago. Offline
Joined: 9 Sep 2010
Posts: 7
Groups: None

Hi there,

 

I loaded the estimate into my project plan in MSP 2007 as cost and material resources. When is a cost resource used?

When I enter % complete, it also calculate my actual cost. I did untick this option but it keeps on doing it. How do I enter my actual costs for each month into the program? How do I get the program not to calculate my actual costs from the % complete, but rather enter it myself on a monthly basis.

 

Regards,

Maarten