BCWP is lower than expected.......my SPI is below 1

No replies
Sam Tan
User offline. Last seen 13 years 51 weeks ago. Offline
Joined: 6 Dec 2010
Posts: 2
Groups: None

Hello,

i'm trying to do EVM for a project for the month of November.  i filled in the actual hours for all my tasks for the month.....(for all the people), and put zero actuals when that task was not worked on but was scheduled to be worked on.

now, when i'm looking at my "Task sheet", i see the following.  (i'm concerned about the second major tasks in bold).  I know we're not behind schedule but how can i increase my BCWP to artificially increase my SPI?

 

 

BCWS BCWP ACWP SV CV
$0.00 $0.00 $0.00 $0.00 $0.00
$60,841.86 $60,670.96 $48,947.07 ($170.89) $11,723.89
$45,791.52 $38,638.56 $28,839.89 ($7,152.96) $9,798.67
$0.00 $0.00 $0.00 $0.00 $0.00