Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Wrong total float

No replies
Ali Alali
User offline. Last seen 9 years 6 weeks ago. Offline
Joined: 9 Nov 2014
Posts: 11

Dear Engineers,

Can i find an answer for my problem :

when i press F9 to attain the progress ,anticipated finish date goes to a logical date (in my project status)while total float is given me a misleading figure and not comply with anticipated finish date.

Finish date activity has  logic date and total float but overall project dont have a logic total float

Many thanks