McDermott Caspian Contractors Inc Planning Engineer

START Date: 
June, 2003
END Date: 
October, 2005
-     Project planning and cost scheduling, issue WBS, S-Curves, resource histograms, project assessment and reporting system;
- Performance indices calculation (weekly/monthly) in line with the corporate procedures;
- Maintain permanent communication with the client’s project controls dept and management for schedule/progress sanction.
- Train local employees; supervise progress reporting system;
•     Achievements:
-     Baku West Azeri Topsides: development of detailed work schedules (Lev 4) for specific WBS, overall project baseline revision – client BP.
-     MERCON Steel Structures, Netherlands: East Azeri Drilling Facilities installation Baseline – Apr/2005 (Integrated Project Team: BP-KCAD-McDermott) – client BP.
-     MERCON Steel Structures, Netherlands: West Azeri Drilling Facilities installation Baseline – Apr/2004 (Integrated Project Team: BP-KCAD-McDermott) – client BP.