Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Dy,Planning Manager, Ramky Infrastructures Ltd, Nitesh Hyde Park

START Date: 
October, 2010
END Date: 
June, 2011

·         Creating WBS of the Project on regular basis as per changes in the design and other additional activities.

·         Calculation of manpower and resource for the Project and Allocation of resources specific for the project

·         Preparing Cash flow Statement for the project using Primavera.

·         Gather all data and information required for effective planning/scheduling, monitoring and controlling the execution of activities of the project using Primavera (P6), MS Office, etc

·         Calculating the efficiency of the manpower and the utilization factor of all deployed equipment based on the actual progress and actual manpower/equipment loadings.

·         Project Tracking through schedules on daily and weekly basis.

·         Tracking of WIP on regular basis, preparing bar graphs for the same.

·         Budgeting, costing and managing fund flow requirement for the project.

·         Preparation of Status reports, Monthly review (MRM) & (PEP), MIS of projects and overall reviewing with Senior Management for progress, material requirements at site.

·         Monitoring and reporting all important project events such as delays, variations in BOQ, extension of time .

·         Preparation of Variation Statement and all other activities pertaining with the Planning process involved in a project.

Experience Hours (Planning & Scheduling): 
4100
Experience Hours (Cost Management): 
4100

Market Place

No results found... (try selecting a different content filter)