Senior Planner, Bombardier, Gautrain
START Date:
December, 2007 Achievements
- Develop and baseline the Communications and Automatic Fare Collection Program integrating this into the Master Program which consists of 10 other interproject linked sub-system programs
- Appointed Master Scheduler & Primavera Administrator requiring sole ownership of the live databases as well as Primavera administrative duties
- Project Controls senior scheduler, responsible for collating progress and producing monthly progress reports for senior management as well as the client
Key Responsibilities
- Develop, progress and report on Automatic Fare Collection Program and the Communications Programmes using Primavera P6
- Maintain, update and progress other subsystem programs such as Signalling, Power Supply Distribution and Vehicles (Passenger Cars) programmes collating information from Engineering, Procurement as well as installation departments
- Manage, and monitor subcontractor reporting ensuring their schedules and monthly progress information is accurately reported.
- Produce, analyseand maintain reports such as Schedule Milestone Reconcilation Matrix, Key Event Indicator Report, Milestone Status S-Curve graphs, Total Program S-Curve Graphs, Key Quantity Reports and Graphs and high level Management Schedules.
- Report actual performance and variance against the plan, forecast performance and the critical path.