Planning/Project Engineer, Siemens, Electrical substations
START Date:
January, 2007
END Date:
June, 2009 - Coordinated with the internal departments for the preparation of drawings for the Substation primary engineering works. Monitored the site installation of these works.
- Coordinated with the Client’s consultants for the approval of design drawings.
- Assisted the Project Manager in selection of sub-contractors.
- Monitored the sub-contractor works of services such as Fire Protection systems, Air conditioning and lighting works in the substation to ensure compliance with the schedule.
- Prepared Project execution plan with Primavera software.
- Preparing monthly & fortnightly progress reports as per client’s requirements.
- Attended Client meetings in the absence of the Project Manager.
- Monitoring defect clearance, handling warranty issues and final closeout documentation works as per DEWA (Dubai Electricity & Water Authority) requirements.
- Company:
- Industry:
- Job Role:
- Project:
- Region: