Planner and Senior Planner, Tipakorn, Connecting Bangkok Southern Ring Road and Industry Ring Road

START Date: 
June, 2004

Created Baseline for Master Schedule and Narrative Schedule.

Writing Monthly Report and Monitoring Schedule.

Cost Estimate for Evaluated Sub Contractor and NewItem on Site.