Construction Planning Engineer, SADRA (Iran Marine Industrial Company), South Pars Gas Field Development Phases 1 / Offshore Facilities (EPC Package)
START Date:
March, 2001
END Date:
February, 2003
KeyDuties:
· Preparation of Construction Appraisal Sheet.
· Preparation of level 4 Detail schedules for Various Disciplines in Construction phase.
· Preparation of Monthly Progress Reports, Productivity Curves and Look-ahead Schedules.
· Preparation of Weekly Progress Reports, Production “S-Curves”.