Planning Engineer / Quality Control Engineer / Quantity Surveyor, DM Consunji Inc., Intermed Corporate Center / PNCO Housing Project

START Date: 
February, 2005
END Date: 
October, 2006

D. M. Consunji Inc.
2218 DMCI Plaza Chino Roces Extn.
Makati, Metro Manila

Duties          :     ●Administered quality and quantity inspections as regard to concrete
mixture and reinforcing bars and witnessed the testing of materials to ensure results were in compliance with the specification requirements.
●Coordinated with the structural designers and subcontractors details affected by other items as construction work progresses.
●Supervised daily construction activities and ensures that plans and specifications are observed.
●Evaluated the monthly progress billings of sub-contractors.
●Prepared materials requisitions, reports, memos and correspondences and maintain records.
●Revision of Schedule for architectural as required at jobsite.
●Involved in quantity estimates for the materials requirements for structural and architectural at site.
●Assisted in Handover of Units to the Owner for final Acceptance.

February 2006 – October 2006
Position     :     Quality Control Engineer – Structural Works / Site Engineer - Architectural
Project          :     INTERMED CORPORATE CENTER PROJECT
               Madrigal Business Park, Alabang, Muntinlupa City
Owner          :     Intermed Marketing Inc.
Project Description:     17th Story building with Roof deck and 2 Basement it is consists of 5 levels for Parking Area, 8 levels for rentable Area, 3 levels for Office Area and Penthouse as Residential by the Owner.
Project Cost     :     Php 875,000,000.00

August 2005 – February 2006
Position     :     Office Engineer / Site Engineer / CQC Structural
Project          :     PNCO – HOUSING PROJECT
               Camp Crame, Quezon City
Owner          :     Philippine National Police (PNP)
Project Description:     Five storey building with Roof deck consist of 88 residential units having 35 sqm floor areas from 2nd to 5th level and ground floor to be used as parking area while the roof deck is for laundry and washing area.
Project Cost     :     Php 75,600,000.00

February 2005 – August 2005
Position          :     Civil Engineer II – Planner/Scheduler
Estimated of civil and architectural works for prospective clients.
               Assisted in the preparation of bidding documents.
 

Market Place