Descon Engineering Limited Planning Engineer

START Date: 
July, 2007
END Date: 
April, 2009
3-Employer: – DESCON ENGINEERING (Pvt.) Ltd.

(a) Project: – Kachhi Canal Project (KC-03) Jul 05, 2007 - Aug 31,2008
Taunsa Barrage – Kot Addu.

Scope of Work: –
Head Regulator, Divide Wall, Flared out Wall, Silt Excluder, Silt
Ejector, Rectangular Channel & Trapezoidal Section of Canal.

(b) Project: – Mangla Dam Upraising Project, Sep 01, 2008 - Apr 30,2009
Mirpur, Azad Kashmir.

Scope of Work: –
Main Earthen Dam, RCC Emergency Spillway,
Under Water Toe Weight Filling. etc.


Designation :– Planning Engineer

Job Responsibilities:-

•     Estimation of Work Scope.
•     Preparation of Site Mobilization Plan.
•     Preparation of Level-V Plan on site.
•     Preparation of Clause-14 Schedule.
•     Preparation and updating of Material/ Equipment/ Manpower
Requirement Plan.
•     Preparation of Material Wastage Reports on weekly and monthly basis.
•     To generate 4-week and 3-month look ahead schedules.
•     To update requirement of manpower, direct materials, direct consumables and equipment based on 3-months look ahead plan.
•     To generate discipline-wise progress and efficiency reports on weekly and monthly basis.
•     To generate cost comparison reports.(i.e. formwork, Asphalt, bricks etc.)
•     To generate earned v actual cost analysis reports.
•     Preparation of BCTC.
•     Preparation of Bottleneck Summary Report.
•     Analysis of Histogram, Critical Path and S-Curve.
•     To update Planning Manager about ongoing activities on different areas on site.
•     To keep myself fully aware of the activities being carried out at Site and also availability of work front, by making frequent visits to the site.