Sakhalin Energy/Shell Senior Planner
START Date:
June, 2004
END Date:
January, 2007 Initially employed as Senior Planning Engineer for the Central Cost & Planning Dept with prime responsibility for the Offshore Scope of Work. This included the Fabrication & Installation of 2 Offshore Platforms of 24,000 & 28,000 tonnes, Tanker Loading Unit and the Fabrication & Installation of 2 additional modules onto an existing Platform. Subsequently transferred to the Offshore Project Group to carry out the same function. Responsible for reviewing, collating & reporting information from the Site Planning Engineers on Status & Progress. Preparation of the Offshore integrated schedule and the monitoring of Interfaces.
Systems Used: P3, Microsoft Project
Systems Used: P3, Microsoft Project
- Company:
- Industry:
- Region: