Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Makati Development Corporation Estimator

START Date: 
April, 2006
END Date: 
August, 2007
B.     MAKATI DEVELOPMENT CORPORATION - MDC (GENCON)
a)     Anvaya Cove is Ayala Land’s first leisure community project.
A 320 hectare master planned seaside residential resort
community comprising several neighborhoods of high – end
residential lots, luxury villas and multi – dwelling units.

April 27, 2006 – August 10, 2007
Location: Brgy. Mabayo, Morong Bataan

Engineering and Planning Department
Position: Planning/Estimator

Duties and Responsibilities:
•     Prepare budgetary estimates, quantity take-off and bill of quantities.
•     Evaluates proposals/estimates submitted by suppliers and subcontractors.
•     Evaluates change orders, budget vs. actual accomplishment.
•     Updates materials and construction costs.
•     Prepares cost analyses of all work items.
•     Attends Pre-bid conferences.
•     Prepare periodic report as needed.
•     Performs other related duties that may be assigned from time to time.
•     Ensures the implementation of the quality plans and objectives of the department and project
•     Performs tasks in accordance with the processes defined in the company’s QEHSMS Manual.
•     Preparing project schedule in Primavera Project Planner (P3).
•     Monitor’s and checks various activities of the project, i.e. material control, structural, architectural of RFI’s/CFI’s.
•     Monitors quality of subcontractor’s accomplishment in accordance with approved specification.
•     Preparing points of coordinates for land development and structure.
•     Preparing the power point presentation for Executive Committee meeting.
•     Prepare monthly Project Director Report to be submitted to owner.

Market Place