Samsung Heavy Industries Planning Manager

START Date: 
April, 2008
Manager (Planning) for Samsung Heavy Industries Co. Ltd.,

Project Handled :      
- Seadrill 1 & 2 - Drillship Commissioning (Saipem 10K Series)
- TCM 1 & 2 - Drillship Commissioning (Saipem 10K Series)
- Petrobras I & II - Drillship Commissioning (Saipem 10K Series)
- Pride 1 & 2 - Drillship Commissioning (Saipem 10K Series)

Roles and Responsibilities :

-     Working as Planning Manager for Topside commissioning activities of drillships (dual / single drawwork), 5th Generation BOP, Operating Depth in Water 10,000 Ft, Drilling Depth upto 37,500 Ft

-     Co-ordinate with Topsides equipment supplier NOV, Class, Clients, Internally with Project Management, Procurement, Engineering, Quality Control, and Hull Interfacing

-     Baseline Commissioning Schedule preparation based on inputs from NOV manpower mobilization plan, construction plan, Hull Utility Supply Plan, Owner Furnished Equipment supply and with follow-up meetings.

-     Plan and Monitor of Individual equipment Tests like derrick load test, Drawworks Load Test, BOP Trolley Test, BOP Gantry Crane Test, Knuckle Boom Cranes Load Test, AHC Crane Load Test, Hydraracker Main Arm Load Test, CMC Sling Test

-     Monitoring Mechanical Completion, Discipline Mechanical Complete Certificate, System wise Mechanical Completion Certificate and Clients verification in order to start pre-commissioning activities as planned

-     Alignments : Plan and monitor of derrick, hydraracker (upper beam, lower trolley and vertical column), Fingerboards (upper and lower), Guide Track for Dolly, CMC Cylinder & Rail and Derrick Elevator rails, Pipe Handling Catwalk, Riser Handling Catwalk, BOP Trolley, BOP Gantry Crane and Base Plate Trolley

-     Pre-commissioning and commissioning of topside equipments planned based sequence of equipments to be started for final commissioning. This has been achieved by lessons learned from the previous drillship projects.

-     Plan, Co-ordinate and Participating for System Integration Test for Riser and BOP Running, Drilling Endurance / Simulation Test, Mud Circulation Test, Bulk Mixing System and successfully achieved all tests as planned

-     Achieving continuously reduction in duration of Topside Commissioning time with optimistic planning in sequence and parallel commissioning activities.