Saipem S.p.A. Planner

START Date: 
April, 2002
END Date: 
December, 2003
Developing, update and monitor the level 2&3 schedules. S-curves, histograms, KPI’s, productivity, trends, application for progress payment, monthly cost reports, invoice checking.
Issuing and monitoring the change orders and trends for all deviations from budget.
Developing and maintaining the WBS and CBS.
Developing the “Document Progress Register” database to control and monitor the engineering and procurement progress and the “Timesheet System” to record the spent man-hours by WBS and CBS.