Tecnimont Project Controls Engineer
START Date:
November, 2007 As a Project Control / Engineer – Planning, November 2007 till date
PROJECT - 1
Title – Heavy Coker Gas Oil Hydro-Treating Unit, Mangalore India
Client – Mangalore Refinery and petrochemicals Limited, MRPL
PROJECT - 2
Title – Taneco Oil Refinery, Russia
Client – OJSC Taneco, Republic of Tatarstan
PROJECT - 3
Title – 450 MTPD Carbon Dioxide Recovery Plant, Andhra Pradesh
Client – Nagarjuna Fertilizers & Chemicals Ltd
Key Activities & Responsibilities:
• Develop Project control schedule, Summary level schedule and 90 days look ahead schedule at the beginning of the project.
• Develop work progress curves for all engineering disciplines, procurement, construction and overall.
• Develop man-hour loading curves for all engineering disciplines and for overall engineering.
• Monitor and control activities start / finish dates, work progress development, man-hour expenditure and productivity trends.
• Analyze the causes of potential delays and evolve possible corrective action for Project Manager’s approval
• Anticipate potentials and suggest PM for appropriate action to avert it.
• Control the correction effectiveness.
• Control of change order to update schedule.
• Prepare documents for monthly progress report & interim flash report, if required.
• Provide data for the preparation of Project close out Report.
PROJECT - 1
Title – Heavy Coker Gas Oil Hydro-Treating Unit, Mangalore India
Client – Mangalore Refinery and petrochemicals Limited, MRPL
PROJECT - 2
Title – Taneco Oil Refinery, Russia
Client – OJSC Taneco, Republic of Tatarstan
PROJECT - 3
Title – 450 MTPD Carbon Dioxide Recovery Plant, Andhra Pradesh
Client – Nagarjuna Fertilizers & Chemicals Ltd
Key Activities & Responsibilities:
• Develop Project control schedule, Summary level schedule and 90 days look ahead schedule at the beginning of the project.
• Develop work progress curves for all engineering disciplines, procurement, construction and overall.
• Develop man-hour loading curves for all engineering disciplines and for overall engineering.
• Monitor and control activities start / finish dates, work progress development, man-hour expenditure and productivity trends.
• Analyze the causes of potential delays and evolve possible corrective action for Project Manager’s approval
• Anticipate potentials and suggest PM for appropriate action to avert it.
• Control the correction effectiveness.
• Control of change order to update schedule.
• Prepare documents for monthly progress report & interim flash report, if required.
• Provide data for the preparation of Project close out Report.