Senior Planning Engineer, px Limited, Teesside Power Station
START Date:
July, 2001
END Date:
December, 2005 Senior Planning Engineer for px Limited, leading a multi disciplined alliance in the production of detailed resourced Level 4 P3 schedules for the annual shutdown of gas and steam turbine generators. Duties also included monitoring and reporting daily progress, ensuring compliance with system handover deadlines, production of s-curves and productivity data, used to focus effort and maintain tight shutdown windows.
I also spent 2 ½ years as the maintenance planner, which involved the co-ordination of Mechanical & Instrument / Electrical tasks between operations and maintenance staff for all the planned maintenance and defect tasks for the site.
Experience Hours (Planning & Scheduling):
9000 - Company:
- Industry:
- Job Role:
- Project:
- Region:
- Skills & Expertise: