ETA - M & E Division Senior Planner
START Date:
July, 2004
END Date:
July, 2006 Preparation of Construction Programme with Resource Loading & Costing in Primavera P3/P6 - Version 3 & 6, Microsoft Project Planner.
Preparation of Extension of Time Claim & associated Costs.
Preparation of all kind of Contractual letters and to assist Project Manager in dealing all contractual issues.
Preparation of seasonal budget including cash Flow.
Weekly tracking, monitoring and scheduling of works.
Weekly Tracking of Material Approvals & drawing Approvals.
Conducting Weekly Internal Meetings with Construction Manager to monitor the progress.
Day-to-day monitoring of works & preparation of Daily Progress Report.
To find out variation with the planned progress if any, and to work out corrective actions or to prepare backup plans or recovery plans.
Monthly & Weekly Presentations to clients and Internal Management.
Estimating construction materials required for the project and procuring the same.
Preparation of costing details for selected critical activities and tracking with the help of costing Engineer.
Preparation of detailed breakup of material, manpower& equipments required for all the activities and Tracking the same.
Preparation of Extension of Time Claim & associated Costs.
Preparation of all kind of Contractual letters and to assist Project Manager in dealing all contractual issues.
Preparation of seasonal budget including cash Flow.
Weekly tracking, monitoring and scheduling of works.
Weekly Tracking of Material Approvals & drawing Approvals.
Conducting Weekly Internal Meetings with Construction Manager to monitor the progress.
Day-to-day monitoring of works & preparation of Daily Progress Report.
To find out variation with the planned progress if any, and to work out corrective actions or to prepare backup plans or recovery plans.
Monthly & Weekly Presentations to clients and Internal Management.
Estimating construction materials required for the project and procuring the same.
Preparation of costing details for selected critical activities and tracking with the help of costing Engineer.
Preparation of detailed breakup of material, manpower& equipments required for all the activities and Tracking the same.
- Company:
- Industry:
- Region: