statoil Planner
START Date:
November, 1995
END Date:
April, 1999 MW Kellogg Integrated Team, Asgard Project
Asgard Project Onshore Terminal Karsto Norway
On Assignment MW Kellogg Offices London
Develop Level 4 Overall Planning Network EPCS Contract
Engineering Fabrication Construction & Commissioning Activities
Using Primavera P3 Windows NT Making Full Use of Office 97 Software
Linking Access 97 via Btrieve Tables to Primavera Level 1 2 & 3 Roll Up Schedules
Transfer of Data to Company PIMS Information System (Access 97 Based)
Monte Carlo Risk Analysis Primavera Add In.
Nov-1995 Feb-1997 Statoil, Statoil Methanol Project, Senior Planner
Develop an overall Planning Network incorporating existing
Contractors Schedules, linking interfaces between them, creating a System Completion logic and
establishing links to the Commissioning and Start-up Schedule.
To provide a computer module for Progress Monitoring "what if " exercise
Critical Path analysis, Milestone Tracking, Histograms, S Curves etc.
Using Primavera Software P3 for Windows.
Asgard Project Onshore Terminal Karsto Norway
On Assignment MW Kellogg Offices London
Develop Level 4 Overall Planning Network EPCS Contract
Engineering Fabrication Construction & Commissioning Activities
Using Primavera P3 Windows NT Making Full Use of Office 97 Software
Linking Access 97 via Btrieve Tables to Primavera Level 1 2 & 3 Roll Up Schedules
Transfer of Data to Company PIMS Information System (Access 97 Based)
Monte Carlo Risk Analysis Primavera Add In.
Nov-1995 Feb-1997 Statoil, Statoil Methanol Project, Senior Planner
Develop an overall Planning Network incorporating existing
Contractors Schedules, linking interfaces between them, creating a System Completion logic and
establishing links to the Commissioning and Start-up Schedule.
To provide a computer module for Progress Monitoring "what if " exercise
Critical Path analysis, Milestone Tracking, Histograms, S Curves etc.
Using Primavera Software P3 for Windows.