Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Bechtel Senior Planner

START Date: 
April, 1999
END Date: 
April, 2001
Bechtel London Office, Project ADNOC, Takreer Front End Engineering
Set up Planning System for Project Using Primavera integrated with Companies
Progress measurement system (Access Database Engineering Documents)
Monitor Progress ,Critical Path Analysis, Look-aheads What-if exercises




Aug-2000 Nov-2000 Bechtel London Office, Karachaganak Project, Detail Engineering
Karachaganak Project Kazakhstan
Detail Engineering Petro Chemical Project Joint Venture with Samprogetti
Take over Lead Project Planner role in closing Stages of Project
Maintain existing schedules levels 1 2 and 3, Close out Packages & Handovers
Progress Tracking of remaining documentation


Apr-2000 Aug-2000 Bechtel London Office, Equinix European IBX Development Project
Develop Level 3 EPC schedules for Internet Exchange Centres in 4 European Capitals. Set up
Engineering & Procurement Databases using Access linked to Primavera networks to track
deliverables & provide business management graphics . Set up P3 networks to enable use of
"Monte Carlo" Risk analysis provide reports from same. Provide usual standard reports Critical
Path, 30 Day lookaheads etc

Jan-2000 Apr-2000 Bechtel Abu Dhabi, Taweelah B Power Plant, Commissioning Planner
Co ordination of Commissioning Activities Producing Plan of the Day schedules, Maintain Level 3
Schedule closely monitoring Construction interfaces establishing Priorities Provide Management
Graphic reports on Systems handover Status. Tracking reports on component Parts i.e MOV’s ,
Loops Status etc.

Apr-1999 Jan-2000 Bechtel Hammersmith Office, Borouge Project, Abu Dhabi
          Develop Engineering level 3 schedule & assist in development of Construction Level 4 schedules
in Primavera, integrating with Companies Engineering "in house" Microsoft Access work
measurement system (EPPR) and Site based work measurement System (Team Works) Provide
system support for P3, resource levelling, network logic analysis level 1 2 & 3 rollups etc
Successful Completion of Companies in house Project Controls University Programme.

Market Place

No results found... (try selecting a different content filter)