Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Senior Planner, Woodside, NWS Developments

START Date: 
March, 2009
END Date: 
August, 2009

 

1. 16-3-2009 to current

 

 

Project Details

 

 

 

 

 

 

 

 

 

 

 

Woodside Energy Limited. http://www.Woodside.com.au

240 St George Terrace. Perth.

 

1. Till Dec 2010 as Senior Planner Offshore- reporting to Project Services Manager and now to various Opportunity Leads.

PLUTO LNG Projectat Burrup Peninsula –Consisting the 4 Tcf Pluto Gas from 5 subsea wells 800 Mtr. deep, flowing to Platform thru 2 20” flow lines(27KmLong) to a piles jacketed platform Structure(6100T) and then to shore thru 36”trunk Line(180Km Long) with a 6”MEG line. The gas then processed at Plant in shore.

 

2.Till May 2011 functioning for AC3.5 Review preparing all documents including risk analysis for Functional Review with JV for Greater Western Flank Project.

 

3. Currently Looking after all development Projects to AC3(Concept Select Review) for North West Shelf Asset like Egret Oil Development, Echo-Yodel Decomm, Lambert Hermes Debottlenecking, Eastern Flank Etc.

 

 

  • Developing and managing all Overall Level-1 Schedule, Level-2 Schedule for all activity Centres (Platform, Pipelines, D&C, Subsea, BMF & PAN Projects) & Level 3 (in house-built)Schedules for Drilling & Completions, Pipelines pre-Commissioning, Hot Comm. Activities, Pre-operations, Systems, Health & Safety, Assurance, Environment , Pipe repair systems, etc.
  • Managing, Revising planning statistical reports based on daily, weekly & monthly progress inputs from various activity centres from remote centres (Platform, Subsea, D&C, Pipelines, Jetty etc.) and roll up to Level2, Level1 &Level 0 for various reporting like Weekly, Monthly reports, CEO reports. and all presentations.
  • Update the Level 1 Master Schedules for overall progress on a monthly basis using Milestone Professional. Prepare Planning Dossier during Re-baseline as part of annual budgeting.
  • Prepare and co-ordinate with necessary Interface Schedules for Upstream & Downstream Works, ICSU Schedules, System Run Down Curves Tracking for UP/Down Streams, Traffic Chart diagrams, Flow charts etc based on management decisions & assumptions and present to activity centre managers for further proceeding.
  • Prepare Planning Schedules upon liaising with Engineers, conduct Risk workshops and Risk Analysis and Prepare Schedule Basis document for Assurance review. Present the risk mitigation/Opportunity analysis document as a result of Risk Analysis.
  • Periodical base lining of all above schedules based on the schedule and budget revisions with necessary changes in S-curves based on revised weightages (as applicable). Prepare & manage S-Curves, Tables, Rundown Curve, Skyline Chart etc.

Market Place