Senior Planner, Intercede, LNG Plant
START Date:
March, 2007 2007 - Present Intercede Houston, TX
Consultant
Two phase effort regarding an LNG gasifier and pipeline. Primarily schedule risk assessment utilizing data from un-sophisticated sub-contractors. Software used - Pertmaster 8.53 and Primavera 6.7.
Schedule risk analysis for a pipeline replacement program. Multi-project effort entailed re-casting one project schedule and developing basic metrics, validating existing systems and suggesting improvements for the other projects.