Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Hyundai Construction & Engineering Project Controls Engineer

START Date: 
September, 1997
END Date: 
June, 2002
1.     Work activity analysis for substantiation of contractual Claims including preparation of “as built” versus “scheduled” programmes showing all instances of delay and disruption to the critical path activities of the Works.
2.     Preparation of Claim data for temporary access roads for excavation to the Regulating Pond. (Including compaction requirement variations issued by Engineer)
3.     Preparation of Overbreak data for underground excavation (TBM and DBM work).
4.     Daily Activity record data to describe sequence of work.
5.     Arrange and manage overall schedule, manpower allocation plan, equipment allocation plan and checking the critical point to keep the progress on schedule.
6.     Arrange and manage Work Programme, two weeks look ahead schedule, 2 months look ahead schedule.
7.     Monthly progress payment data.
8.     Method statement / works procedure especially for underground works.

Market Place

No results found... (try selecting a different content filter)