Nippon Steel Senior Planner

START Date: 
November, 2005
END Date: 
April, 2007
South Sumatra - West Java (SSWJ) 32" Offshore Gas Pipeline Project - CP2.

- Preparing schedule and pipe loading scenarios to be implemented in relation to daily single joint welding productivity and barge window of availability using P5;

- Preparing transport barges schedule and sequences related to number of available barges and required traffic arrangement during pipelaying activity;

- Preparing pipes coating and thickness identification report;

- Preparing installed pipe joints identification report. Preparing returned pipes/ surplus construction material report;

- Preparing pipes delivery status report for each material barges sent from load-out yard;
- Preparing periodic progress report regarding construction activities including but not limited to: Near Shore Pre-trenching Works, Offshore Pipelaying Work and Post-trenching Works;

- Preparing weekly EPC and Overall Progress Report from MDR, Procurement Status Report and Construction Daily Progress Report;

- Preparing Project Coordination weekly Minutes of Meeting. Preparing weekly internal Minutes of Meeting;