Wood Group Planner

START Date: 
March, 2007
END Date: 
March, 2009
Responsible for all planning related activities for initially, the Hummingbird FPSO, from fit out in Rotterdam shipyard during construction to Sailaway, Hookup, Commissioning and eventually into production.
Once the Hummingbird platform was completed I then moved on to the Voyageur FPSO project and carried out the same planning work for that project, again from Rotterdam to anchoring in the North Sea. The planning tool used was MS Project and Maximo for maintenace.