SNAMPROGETTI – Milano Planner

START Date: 
October, 2001
END Date: 
June, 2002
Project:-          BHIT GAS FIELD DEVELOPMENT PROJECT, PAKISTAN.
Client:-          LASMO OIL PAKISTAN LTD.
AS Sr. PROJECT CONTROL ENGINEER
Major Responsibilities               
I.     Preparation of Level II construction schedule at Primavera Project Planner.
II.     Verification & Analysis of Contractor Level III & IV construction schedule.
III.     Monthly feasibility preparation on the basis of work frontage, availability of equipment and material.
IV.     Progress Monitoring & Report Generation for Client and Head Office.
•     Activity wise progress reports on the basis of quantity using (SICON) S.P in house software.
•     Comparisons between Actual & Earned Man-hour for productivity and time require complete the balance job.
•     Update the schedule & generate forecast for next week using Primavera Project Planner.
•     Preparation of S-curves and manpower histogram.
•     Narrative report for each activity.
•     Bottle neck presentation both due to client & Head office.
V.     Verification & analysis of contractor Weekly & Monthly progress report.
VI.     Analysis and verification of Contractor’s invoices & claims.