Foster Wheeler Italiana Project Controls Engineer
START Date:
October, 2004
END Date:
March, 2006 Involved in the realization of a combined cycle power plant (foreseen duration 22 months). In charge for planning, analysis and tracking of the project schedule (engineering, procurement and construction), weekly/monthly progress reports. Client: RATIE/MERLONI
- Company:
- Industry:
- Region: