Leighton Australia Planner
START Date:
February, 2009 3 month contract to tidy up hacked P6 programme with too many inexperienced users and rudderless contract planners.
Programme was fully resourced, using timesheets, and their primary actuals and forecasting repository & tool.
Required some detailed analysis into data, and many hours of correcting erroneous data, cost plugs then aligning of P6 cost values with the G/L and excel based Cost Analysis Report.
Baseline also needed to be updated to to bring it into alignment, along with the correction of the Stored Period data.
Programme was fully resourced, using timesheets, and their primary actuals and forecasting repository & tool.
Required some detailed analysis into data, and many hours of correcting erroneous data, cost plugs then aligning of P6 cost values with the G/L and excel based Cost Analysis Report.
Baseline also needed to be updated to to bring it into alignment, along with the correction of the Stored Period data.