Bentini S.p.A Project Controls Engineer
START Date:
October, 1998
END Date:
September, 1999 Overall Planning, Scheduling, Forecasting, Monitoring progress, training the concerned persons for various Project Management aspects, co-ordination with Client, Consultants, Sub-contractors & our management for controlling all six pumping stations from Khartoum.
PROJECT: PUMPING FACILITIES FOR MUGLAD BASIN OIL DEVELOPMENT PROJECT-SUDAN.
CLIENT: TECHINT - SAIPEM JV - ARGENTINA / ITALY.
OWNER : G.N.P.O.C.(GREATER NILE PETROLEUM OPERATING COMPANY)-SUDAN
CONSULTANTS : O.G.P. – MALAYSIA
SCOPE OF WORK: Construction of six Pumping Stations along the 1500 km. Pipeline including all Electro-Mechanical works.(Project Value Approx 48 Million USD)
PROJECT: PUMPING FACILITIES FOR MUGLAD BASIN OIL DEVELOPMENT PROJECT-SUDAN.
CLIENT: TECHINT - SAIPEM JV - ARGENTINA / ITALY.
OWNER : G.N.P.O.C.(GREATER NILE PETROLEUM OPERATING COMPANY)-SUDAN
CONSULTANTS : O.G.P. – MALAYSIA
SCOPE OF WORK: Construction of six Pumping Stations along the 1500 km. Pipeline including all Electro-Mechanical works.(Project Value Approx 48 Million USD)