Saudi Arabian Bechtel Company Project Controls Engineer

START Date: 
June, 2000
END Date: 
February, 2002
As a Construction Planner, responsible for updating and monitoring of 4-Weeks Look Ahead and Monthly Intermediate Schedules. Coordinate with various sub-contractors to track progress and update schedule. Update of commodity curves / metrics for field implementation. And as a Start-up Planner, responsible for daily updates of the Plan for the day activities and updates of bulk commodities instrumental for milestone target completion. Implements Weekly Start-up Percent complete Status Report and updates of Unit 6 through 10 Completion Schedule.