Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Turner Arabia Project Controls Manager

START Date: 
February, 2007
END Date: 
August, 2007
Dar Al-Arkan Program Management Project
•Acting at the Core Team for supervising the planning and control activities of various Dar Al-Arkan real estate projects such as:
Al Qasr Development Project (453,000,000 US$, 977,000m2, Residential) , Al Tilal Project - Phase 1 (77,000,000 US$, 161,000m2, Residential), and Shams ArRiyadh Project (269,000,000 US$, 2,860,000m2, Infrastructure).
•Revision of cost-loaded schedules submitted by contractors.
•Preparation of Dar Al-Arkan Five Year Plan (about 10 Billion US$).
•Participation in preliminary studies of potential real estate project.
•Participation in the preparation of the Project Execution Plans (PEP).
•Preparing the Indicated Outcome Report (IOR) for cost control.
•Participating in the committee for unifying the Work Breakdown Structure (WBS) for all Dar Al-Arkan residential projects.

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.