Planning Section Head, Petrojet (Egypt), Trans-Gulf Crude Oil Treatment
START Date:
May, 1997
END Date:
May, 1999 - Preparing the overall project detailed schedule.
- Preparing & following up look-ahead construction plans.
- Daily, weekly, and monthly follow up of projects through relevant reports.
- Control and coordinate all assignments related to planning and reporting.
- Analyzing delay reasons if occurred and participating in planning the best ways to overcome such reasons.
- Preparing & following up the manpower productivity reports depending on the scheduled figures.
- Following up, updating & revising the project schedule.
- Following up the project requirements of resources.
- Establish planning information on different levels and disciplines for prospects and projects executed by project engineering, and regularly update the planning tools with changes like new activities, no. of man-hours, progress, etc.
- Developing comprehensive selective schedules for all specified activities.
- Planning, reviewing and recommending strategies for most of the engineering projects.
Experience Hours (Planning & Scheduling):
4800 - Company:
- Industry:
- Job Role:
- Project:
- Region: