Doosan Babcock Planner
START Date:
July, 2008 Feb ’09 - Present
Assisting with the Prep and Planning of the Outage for Drax Power Station Selby.
Jul ’08 - Feb ’09
Planning and scheduling on the BCU Project on Hartlepool Power Station, Doosan Babcock being the principal contractor to British Energy.
Assisting with the Prep and Planning of the Outage for Drax Power Station Selby.
Jul ’08 - Feb ’09
Planning and scheduling on the BCU Project on Hartlepool Power Station, Doosan Babcock being the principal contractor to British Energy.