Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

wrong FINISH DATE

I am preparing a recovery program using P6 and I am facing the issue of having a wrong FINISH DATE.

The activity (selected) has remaining duration of 2 days and its predecessor's Finish Date is 25 Sept. With this scenario, I believe the activity has to have a FINISH DATE of 2 days after the 25 Sept - means Sept. 27. But the calculated P6 Finish Date is 23 Oct which is 28 days difference. I have FS relationship. Not only this activity but so many in my program as well. 

You can see in the gantt chart how it behaves.

I tried different Duration type but same outcome.
Why? Can anyone help me? Is there any way to do this? 

Im using a Retained Logic. I think progress override is not a good option as it breaks the sequence of the work.

All calendars are set to 6 days. 

Anyone who wants to check the entire program, I can send. Comment your email.

Thank you planningplanet community.

 

Please see screen shot below:

6997
p6.jpg

6998
p6_2.jpg

6999
p6_3.jpg

Market Place

No results found... (try selecting a different content filter)