wrong FINISH DATE
I am preparing a recovery program using P6 and I am facing the issue of having a wrong FINISH DATE.
The activity (selected) has remaining duration of 2 days and its predecessor's Finish Date is 25 Sept. With this scenario, I believe the activity has to have a FINISH DATE of 2 days after the 25 Sept - means Sept. 27. But the calculated P6 Finish Date is 23 Oct which is 28 days difference. I have FS relationship. Not only this activity but so many in my program as well.
You can see in the gantt chart how it behaves.
I tried different Duration type but same outcome.
Why? Can anyone help me? Is there any way to do this?
Im using a Retained Logic. I think progress override is not a good option as it breaks the sequence of the work.
All calendars are set to 6 days.
Anyone who wants to check the entire program, I can send. Comment your email.
Thank you planningplanet community.
Please see screen shot below:
![p6.jpg 6997](http://www.planningplanet.com/sites/default/files/imagecache/wysiwyg_full_page/wysiwyg_imageupload/56004/p6.jpg)
![p6_2.jpg 6998](http://www.planningplanet.com/sites/default/files/imagecache/wysiwyg_full_page/wysiwyg_imageupload/56004/p6_2.jpg)
![p6_3.jpg 6999](http://www.planningplanet.com/sites/default/files/imagecache/wysiwyg_full_page/wysiwyg_imageupload/56004/p6_3.jpg)
Printer-friendly version
- Login or register to post comments
Send to friend