Cost Loading: Material Type Resource or Expenses?
Hello Gentlemen,
What are you using in Cost Loading of Schedule?
Material TYpe Resource or Expenses?
In the Contractor Side, I prefer to use the Material Type Resource. The purpose is to generate the Earned Value (EV) in which a contractor may earn a progress based from the Budgeted Cost.
I did not prefer to use the Expenses because, Expenses as I understand is the Expenditures in which a contractor planned to spend.
What are your inputs?
Happy Planning.