The situation where a contractor has been awarded two or more different contracts for different phases on the same site must be failry common because I have encountered it three times so far in my career.
It is a recipe for disaster for the Employer because if the contractor causes a delay on Contract 1 which then delays acces to Contract 2 then the same contractor is entitled to an extension of time on Contract 2 on the grounds of employer's denial of access.