Planner & Scheduler, PETROLEUM MECHANICAL EXECUTING & ASSMEBLY JSC, 12/9 OIL AND GAS CEMENT PLANT PROJECT

START Date: 
September, 2009
END Date: 
September, 2010

Ü   12/9 OIL AND GAS CEMENT PLANT PROJECT.

Position: PLANNER/ PROJECT ENGINEER

Description of Project:

·        Investor: Petro Vietnam Nghe An Cement JSC.

·        Places: Hội Sơn - Anh Sơn - Nghệ An

Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
1000

ASSISTANT MANAGER-PLANNING & COORDINATION, TEGA INDUSTRIES LTD, RUBBER PLANT

START Date: 
July, 2012
END Date: 
September, 2013

·         Planning, Generating WBS, Tracking, Resource allocation & Leveling and Reporting.

·         Catch-up Schedule for delay activities.

·         Site Execution, Progress Monitoring & Control.

·         Estimation, Costing, BOQ & BOM.

Experience Hours (Planning & Scheduling): 
2250
Experience Hours (Cost Management): 
0
Experience Hours (Forensic Analysis): 
0

project planner, TOTAL, SURF and TOPSIDES development program Northsea

START Date: 
December, 2011
END Date: 
December, 2012

2011-2012

TOTAL E&P Nederland bv

Project planner

December 2011 to December 2012 working with TOTAL E&P in The Netherlands, planning offshore SURF and Topsides developments programs.

Tools: Primavera P6, Value 160mln Euro.

Location: Den Haag NL

Procurement by ATLAS

Project Controls Lead, Mott MacDonald, Eastern Cape Infrastructure Joint Venture

START Date: 
August, 2013
END Date: 
January, 2017

Project Controls Lead for Eastern Cape Infrastructure Joint Venture (ECI JV), providing EPCM services to Transnet Capital Projects while carrying out various capital projects within the Port of Ngqura, Port of Port Elizabeth and Port of East London.

Senior Cost & Planning Engineer, Makyol-Cengiz Joint Venture, Duhok International Airport Construction Project, Duhok (Kurdistan)

START Date: 
April, 2013
END Date: 
September, 2013

To produce and monitor a computer based program using Primavera (version 6.7) which helps to complete the project on time and within the given budget.

Compile project program, procurement schedule and drawing program

·         Identify key start & finish dates

·         Identify resources available

Planning Engineer, EEI Corporation, Megawide Construction Corporation, EXPANSION OF ADB HEADQUARTERS BUILDING, B-HOTEL QC (A 10-Storey Hotel)

START Date: 
February, 2012

 Participates in the preparation of Project Operational Plan, Master Construction Schedule and PERT-CPM for an Effective Project Planning and Monitoring of the Progress of Works in Project Site.  Details the Schedule based on the present condition/workability of project site.  Resource loading based on the Construction Schedule.  Set-up Monitoring Tools for Efficient Progress Accomplishment. Tracking.

Sr. Planning Engineer, SK Engineering & Construction, Construction of Married Flats Package-12 (Ruwais Housing Complex-ADNOC)

START Date: 
November, 2011

Possess more than 11 years of Professional Experience with several National & Multinational Companies. During this period I was engaged in Delay analysis and Claim for Extension of Time (EoT), Construction, Planning, Monitoring and Controlling for heavy Engineering Constructions like Commercial & Residential Buildings and Oil Pipeline Project (800Km).

PLANNING ENGINEER, SIMPLEX INFRASTRUCTURES LIMITED, DLF SKY COURT

START Date: 
November, 2013

1. Scope Planning (3-months look ahead Programme)

2. Preparing Cost Budget

3. Monitoring Daily Actual Progress

4. Conducting Weekly Progress Meeting

5. Analyse gap between  Plannes Vs Achieved

6. Resource Management (Manpower , Material , Equipments)

Experience Hours (Planning & Scheduling): 
200
Experience Hours (Cost Management): 
100
Experience Hours (Forensic Analysis): 
150

Senior Planning & Cost Control Engineer, Nesma & Partners Contracting Co., Jabal Omar Development Project , Saudi Aramco Security Upgrade Project

START Date: 
April, 2011

Nesma & Partners Contracting Co. Ltd, Jeddah, Saudi Arabia

SENIOR SCHEDULING & COST CONTROL ENGINEER

Nov 2011 – Present

Ñ        Working as a Senior Scheduling and Cost Control Engineer for Saudi Aramco for security upgrade project for 26 (Bulk Plants & Oil Refineries) around Saudi Arabia

Experience Hours (Planning & Scheduling): 
7000
Experience Hours (Cost Management): 
3000
Experience Hours (Forensic Analysis): 
4000

Senior Planning & Cost Control Engineer, Nesma & Partners Contracting Co., Jabal Omar Development Project , Saudi Aramco Security Upgrade Project

START Date: 
April, 2011

Nesma & Partners Contracting Co. Ltd, Jeddah, Saudi Arabia

SENIOR SCHEDULING & COST CONTROL ENGINEER

Nov 2011 – Present

Ñ        Working as a Senior Scheduling and Cost Control Engineer for Saudi Aramco for security upgrade project for 26 (Bulk Plants & Oil Refineries) around Saudi Arabia

Experience Hours (Planning & Scheduling): 
7000
Experience Hours (Cost Management): 
3000
Experience Hours (Forensic Analysis): 
4000