Arun Vasanth
Sudarsan Srinivasan
Working with a Project Management firm as 'Planning Manager' in Bahrain. Job profile included preparing snap shots, project health check, dashboard, status reporting, EOT review, analysis and determination, cost control on approved programme, contractual issues and response to delay notices by Contractor, preparing and maintaining overall cosmic development programme of a township development in progress.
Planning Manager, HAJ Quantity Surveyors SPC, Four Seasons Hotel, Diyar Al Muharraq, Investment Gateway Bahrain, Staff Accommodation Building for 4 Seasons, 27 storey residence tower, Precontract services
Had the fortune to work on prestigious landmark projects as the Four Seasons (partly) and several high rise buildings, infrastructure project, a full fledged township development comprising of 3000 housing units with Primary and secondary infra works, mosque, retail units, etc. on a reclaimed land mass north of Bahrain. As client representatives, my job entails preparing dashboard reports, milestone charts, high level development programme and status reporting and highlighting potential issues both on site and with respect to programme.
Assistant Planning Manager, Kuwaiti Manager's Company, Wadi Al Sail Mall, Al Mazaya Warehouse, Two nos. of 5 storey building, Isa town market restoration
Mostly involved in construction of a shopping mall with cinema and hypermarket facilities at Riffa, Bahrain. Other than that, was also handling programme and monitoring for a warehouse project with specialized flooring and a 5 storey building construction at Hidd. Project management work included maintaining cash-in and out flows for management on all active projects, and provide to accounting / finance to know budget and actual revenue earned and prepare CVC reports, tender master schedule and compilation of submission documents for tender.
Senior Planning Engineer, Forensic Delay Analyst, G.P.Zachariades (Overseas) Ltd., Banader Rotana Hotel, Residency Hotel Refurbishment, STP & DGS at Hidd, Durrat Al Bahrain (Claims), Bahrain Monument (Claims)
Worked as 'Delay Analyst / Senior Planning Engineer' with a Contracting / construction firm which employs more than 5000 people and was / still a market leader in the region. As a delay analyst, my role was to successfully prepare, submit and close out the entitlement requests (time & cost) on projects already completed. Hence, my role was more as 'Forensic Delay analyst' and preparing detailed claim analysis and narratives for submission to Client.
Planning Engineer, Projacs International, 100 Residence Tower, Adhari Park, Marina West, Porta Reef, Sarab Al Areen, Sukoon Tower, Vision Tower
Associated with a Project Management Company and worked on multitude of projects (retail, commercial, villas, hotel, mixed use and high rise) of value more than 150 Million BHD (USD 300 Million). Have adequate experience in Planning, review of EoT, preparing status reports for Client, monthly project reports, using and maintaining MIS for all projects in the country.
Chief Project Control Engineer, PT. Truba Jaya Engineering / PT. Truba Jurong Engineering, GIIC Pelletizing Plant No.2 Project, Kingdom of Bahrain
- Provide and Manage Master and Detail Construction Schedule (start from Fabrication of Mechanical Structure, delivery to middle east and installation activities)
- Evaluate the Man-hour and Productivity, Actual Cost Behaviour, Cash Flow and Contract Change Order
- Manage and Monitor the Actual Cost with Cost Breakdown Structure with Finance Dept.
PROJECT CONTROLS MANAGER, Parsons Brinckerhoff (ME) Ltd, AL-HIDD PHASE III DESALINATION PROJECT
PROJECT CONTROLS MANAGER
AL-HIDD PHASE III DESALINATION PROJECT
PARSONS BRINCKERHOFF, BAHRAIN