Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

EPC Senior Planner

EPC Senior Planner, Sephaku Cement, Central Processing Facilities Phase 1 & 7

START Date: 
January, 2008

I am 27 years old, I have a Bachelor of Commerce Degree in Supply Chain Management, my experience has been in the construction industry, mostly mechanical erection.

I am currently the Project Planner on the Client's behalf, on a Greenfield Turnkey EPC Project in South Africa, where we are constructing a Cement Grinding Facility.

The Turnkey Contractor is a Chinese based firm, thus I am involved in compiling the reports, reporting on progress, and status of the project, coordinating between site activities and the procurement and supply of equipment from abroad.

EPC Senior Planner, Stopford Projects, Green Energy Technology

START Date: 
May, 2008
END Date: 
December, 2010

 

Contract Planning Engineer for the engineering, procurement, construction and commissioning (EPCCM) contract on behalf of Green Energy Technology (GET). The project is to generate electricity by converting segregated solid municipal waste into Syngas through plasma gasification and is to be constructed in Sri Lanka in 2010. Using Primavera P3 for both planning and progress monitoring against a resourced target plan, reporting earned value for individual disciplines against a fully developed work breakdown structure.

EPC Senior Planner, Foster Wheeler, Construction of Cooling Tower

START Date: 
January, 2011
END Date: 
June, 2011

 

Contract Planning Engineer for the FW and Shell alliance based at Stanlow Oil Refinery, Ellesmere Port.  Using Primavera P6 to develop project programmes for Design Engineering and EPCm phases of work at Level 3, then integrating Construction Contractor Level 4 detail and monitoring/reporting progress to the Project Lead Engineers using Project Controls processes.

EPC Senior Planner, Nuclear Technology, Test Rigs

START Date: 
June, 2011
END Date: 
February, 2012

 

Contract Planning engineer & project controls management for the Design, Build, and Operation of Small (25%) and Medium (50%) Scale Test Rigs. Using Primavera P6 for the management of the level 3 project programme and delivery at level 4 by the responsible contractor.

EPC Senior Planner, Jacobs Engineering, Tails Management Facility

START Date: 
July, 2012

 

Contract Planning Engineer responsible for the alignment of schedule with cost on a major EPC contract in the nuclear sector. Utilising Primavera P6 in a planning team environment and responsible for the engineering schedule for several work packages within the overall programme. Also responsible for the development and implementation of an integrated change management process using existing project procedures and change control system.

EPC Senior Planner, Emirates Technical Associates, 220/132/33/22/11kV Substations

START Date: 
March, 2008
  • Prepare / Review and approve / comment / finalize on the Engineering (Design), consultant/vendor, Budget, Procurement, Construction  & Commissioning schedules as submitted and ensure the Schedule is in compliance with the overall project schedule through critical path method and advise the concerned of any deficiencies from standards.
  • Continuously monitor, against approved schedules, the Contractor’s major construction progress and ensure equipment and manpower are adequate or in case of any shortage report to concerned.

EPC Senior Planner, WCT Bhd, Tun Razak Exchange (TRX)

START Date: 
June, 2013

1. Establishing the Baseline Programme

2. Monitoring the daily progress of works

3. Reporting & Presenting the progress to Top Management & Client.

4. Preparing Impacted Cost & Delays analysis for the project.

5. Preparing & compiling of Application of EOT's notification & documents.

6. Revised & Recovery Work Programme.

7. Monitor, Review, Analyse & Realign the Subcontractors progress of works from delays.

8. Guide the young .planner on the above.

EPC Senior Planner, Siemens, Railway Infrastructure

START Date: 
March, 2006
END Date: 
May, 2007

Design and implementation of Client planning and scheduling systems for the activities
coordination for the Algiers subway consortium: Vinci GP, Siemens TS, CAF.
Worked in a pressurized environment with professionals from diverse technical and cultural backgrounds.
Gantt Charts and Time-Distance diagrams (Tilos.)
 

Experience Hours (Planning & Scheduling): 
2000

EPC Senior Planner, WorleyParsons Kz, SULFUR EXPAN

START Date: 
July, 2008
END Date: 
August, 2010

Functional Duties:
Provide information to senior management to enable effective project delivery.
Provide schedules from summary to detailed level which optimize expenditure of time, resource utilization and cost.
Regular project reports on current status of projects.
Identify areas of concern and subsequent recovery action to minimize adverse trends.
Specific Duties and Responsibilities:
Prepare schedules to reflect the work to be undertaken in line with the required Work Breakdown Structure.
Undertake resource loading of schedules in order to produce manpower histogra

EPC Senior Planner, IMPSA, HYDRO PROJECT

START Date: 
September, 1998
END Date: 
May, 2013

Planificación y control de Proyectos.
Definición de WBS y Operaciones.
Control de avance real vrs. planificado.
Gestión del Valor Ganado.
Especialista en el sistema de proyectos de SAP (PS).
Soporte a usuarios finales de SAP.
Cursos de Administración de Proyectos con SAP.
Formación de la oficina de control de proyectos.
Análisis de Procesos de Gestión de Proyectos. 

Market Place

No results found... (try selecting a different content filter)

Syndicate content