Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Resource Leveling

Why so many poor schedules?

Why so many poor schedules?

Schedule logic is not the issue, what makes our schedule models so poor is how we deal with resources. Without resources nothing is done.  Schedules that do not take into account all resource constraints are incomplete and most probably wrong.

We favor simplicity over substance and give the project manager very poor schedules he must manually adjust as soon as he realized the plan is no good.

Determine the longest path of a resource leveled schedule in P6

Unfortunately when it comes to resources and resource leveling, P6 model is absolute. P6 doesn’t calculate the float correctly and the longest path will not be accurate since the late and early dates will not change after leveling.

Primavera P6 doesn’t take in consideration the new dates after the leveling in calculating the total float or the longest path, to illustrate further if we have a project consists of three activities A,B & C and they all share the same resource and each activity 5 days duration and the project completion after 15 days.

How to Level Resources / Resource Leveling without changing Project Finish date in Primavera P6

Normally when we Level Resources, Primavera will delay an activity so that Resource is not overloaded. It can make Project Finish date delay.

How can we make Project Finish date not delay? I’ll explain in this article.

Market Place

No results found... (try selecting a different content filter)

Syndicate content